The geotechnical assessment revealed some organic matter that must be removed from the property. Also, an amended floodplain bylaw was passed by the City which requires us to build up the site by 1.2 metres. These are both extra costs for the project. In addition, parking and landscaping must be included in the budget. These items greatly reduce the budget available for the actual building. The Cedars Christian School Board is holding an extraordinary Society meeting on Dec 12th, 2011 to discuss and decide between two options:
1.) To further fundraise in order to build a gym which would require approximately another $1.1 million
OR
2.) To build what we can with the $2.9 million we have which would include a home ec room and wood shop & washrooms
Please come out to the extraordinary meeting to learn more and to provide your input on this very important decision.